Installed Capacity |
: |
91,4 MW (2 x 45.70) |
Annual Energy Generation |
: |
330 Million kWh |
Radius and Length of Headrace Tunnel |
: |
Radius: 4.0 m, Length: 8.0 km |
Lenght of Penstock |
: |
350.0 m Long Underground Tunnel of 64 Degree Incline-a First In Turkey |
Project Start Date |
: |
January 2008 |
Project Completion Date |
: |
Mayıs 2010 |
CO2 Emmission Reduction / Avoidance |
: |
187,000 Metric tons / year |
Number of Trees Needed for Equivalent Amount of CO2 Reduction |
: |
660 |
Number of Homes to Supply Electricity |
: |
183 |
Certificate |
: |
Verified Carbon Standart (VCS) |
PLANNING, PROJECT, CONSTRUCTION AND MECHANICAL WORK 100% BY TURKISH ENGINEERS AND TURKISH COMPANIES.