Installed Capacity : 36 MW (3 x 12.00)
Annual Energy Generation : 150 Million kWh
Radius and Length of Delivery Tunnel : Radius: 4.0 m, Lenght: 7.0 km
Lenght of Penstock Pipe : 65.0 m
Project Start Date : Januay 2009
Project Completion Date : December 2010
CO2 Emmission Reduction / Avoidance : 300
Number of Trees Needed for Equivalent Amount of CO2 Reduction : 500
Number of Homes to Supply Electricity : 83
Certificate : Verified Carbon Standart (VCS)
 
PLANNING, PROJECT, CONSTRUCTION AND MECHANICAL WORK 100% BY TURKISH ENGINEERS AND TURKISH COMPANIES.